Commercial Fit-Out IT Checklist: From Design Drawings to Move-In Morning

Technology tasks that landlords, tenants and project managers should schedule during office fit-outs so the suite opens on time and works on day one.

  • By Ali Sedighi, MBA
  • Reviewed 2026-10-06
  • 5 min read

Office fit-outs are choreographed around trades: demolition, framing, electrical, ceilings, flooring, furniture. Technology is often the last item on the schedule and the first to be blamed when the suite opens late. Carrier installations take weeks, cabling must be done before the ceilings close and move-in weekend leaves no room for surprises. This checklist walks through the technology tasks in order, for landlords preparing base-building suites and for tenants moving in.

At design stage: involve IT early

Bring the technology provider into the project when the floor plan is still flexible. Layout decisions determine where outlets go, how many are needed, where the rack lives and how the carrier reaches it. A late change can mean opening finished walls.

Agree the list of requirements: number of workstations, meeting rooms, phones, printers, access doors, cameras, wireless coverage and any special equipment. Share it with the architect and the electrical contractor.

Carrier ordering and the demarcation point

Carrier lead times can run from weeks to months depending on building access and construction needs. Place the order as soon as the lease is signed and the suite is identified, and confirm with the landlord where the carrier enters the building and how it reaches the suite.

Document the demarcation point, the riser path and any landlord approvals needed. Ask for a confirmed installation date in writing and keep a contingency, such as cellular internet, for opening week.

Structured cabling and the rack

Specify category 6A cabling for workstation and wireless drops, with outlets sized to the furniture plan, and fibre where backbone runs require it. Plan the rack location with space, power, cooling and access in mind, and leave room for growth.

Require test results for every cable, delivered before ceilings close. Label both ends. Cabling mistakes found after finishing are expensive and delay occupancy.

Wi-Fi, security and building systems

Wireless design should follow the final furniture layout, with access points placed for coverage and capacity. Plan door access, cameras and intercoms alongside, and coordinate with the landlord's base-building systems so tenant equipment integrates without compromising building security.

Check any requirements the landlord has for network separation, insurance or approved contractors.

Meeting rooms and collaboration

Meeting rooms are where first impressions are formed. Specify displays, cameras, microphones and room systems compatible with the platform your staff use, and design simple controls. Test each room with a real call before move-in.

Record the room setup in a one-page guide and leave it in the room. Staff are more likely to use well-documented rooms.

Move weekend

Prepare a detailed plan: equipment delivery, rack installation, network cut-over, workstation placement and testing. Assign a person to each task, confirm elevator and loading dock bookings and schedule the carrier cut-over for a date well before staff arrive.

On the first morning, have technicians on site to resolve printer, phone and login issues. A visible support presence in the first hours reduces frustration.

Decommissioning and handover

Old equipment must be wiped and removed securely, with certificates of data destruction. Return leased equipment, cancel services at the old location and update the asset register.

Hand over the final documentation: drawings, test results, equipment lists, credentials and support contacts. For landlords, keep a copy for the next tenant.

Mistakes that delay opening day

Typical delays come from five sources: a carrier order placed after the lease commencement date, cabling run before the final furniture plan, a rack room that is too small or too hot, meeting-room equipment ordered but never tested and a move weekend with no named owner for each task. Each is cheap to prevent and expensive to fix. Put the carrier date, the cabling test report and the move-weekend plan on the project schedule next to the electrical and flooring milestones, where the whole team can see them.

Checklist

  • Involve the technology provider before the floor plan is final
  • Order carrier service as soon as the lease is signed
  • Document the demarcation point and riser path
  • Specify cabling, rack location, power and cooling, and require test results before ceilings close
  • Design wireless coverage from the final furniture plan
  • Coordinate door access and cameras with base-building systems
  • Test every meeting room with a live call
  • Wipe and certify old equipment and hand over complete documentation

Where this lands by property type

Commercial Landlords

Commercial landlords compete on building quality: reliable connectivity, secure access and a smooth fit-out process. Technology gaps show up in vacancy and renewal rates. Typical exposure: tenants asking for connectivity options the building cannot provide.

Co-Working Operators

Co-working runs on member experience: Wi-Fi that works, doors that open and a printer that prints. Operators also host many separate companies on one network. Typical exposure: member traffic needing isolation from operator systems.

Property Developers

Developers define the technology a building lives with for decades. Decisions made at design stage, on risers, cabling and carrier access, are expensive to change after turnover. Typical exposure: telecom rooms sized too small and placed without carrier input.

Next step: a building technology survey

PropertyIT is a sub-brand of SAZ.ca, led by Ali Sedighi, MBA, combining senior-partner strategy with hands-on IT delivery for property teams. If this article describes a situation in your buildings, book a free 30-minute consultation: call (604) 632-4959 or email info@SAZ.ca. We will give you a plain-language view of your options, and a fixed-price scope if you want one. No lock-in, no pressure and no obligation.

Frequently asked questions

How long before move-in should we order internet?

As early as possible. Lead times vary, and carrier access can take weeks to months, so order when the lease and suite are confirmed.

Who is responsible for cabling, the landlord or the tenant?

It depends on the lease. Review the landlord work and tenant work schedules and agree the split in writing.

Can PropertyIT manage the whole IT scope?

Yes. Our Commercial Office IT Fit-Outs service covers design, procurement coordination, cabling oversight, move weekend and day-one support.

Do you help landlords with vacant suites?

Yes. A standard technology specification and pre-installed cabling make suites easier to lease and faster to occupy.